Steel building timeline from planning to handover

Cold-rolled galvanised kits typically deliver in 3 to 6 weeks. Hot-rolled CE-marked EN 1090 portal frames take 6 to 10 weeks to detail, fabricate and coat, with crane erection and cladding taking 1 to 3 weeks on a cured concrete base. Commercial projects also require 12 to 24 weeks upfront for planning permission, Fire Safety Certificate, DAC and BCMS commencement.

Realistic Irish schedules across planning permission, FSC/DAC, shop drawings, EN 1090 steel fabrication, concrete pads and crane erection.

Free, no obligation. One local fabricator prices it, not five.

  • 12–24 wkscommercial planning, FSC & BCAR
  • 3–6 wkscold-rolled galvanised delivery
  • 6–10 wkshot-rolled EN 1090 fabrication
  • 1–3 wkscrane lift & composite cladding
Fabricator wearing a welding visor and leather gauntlets grinding a heavy structural steel beam in a workshop

Stage-by-stage Irish build sequence

  1. Weeks 1–16: Planning, FSC, DAC & ESB application. Lodge full planning drawings (8-week statutory decision plus 4-week appeal period if no further info requested). Lodge FSC and DAC concurrently once design freezes.
  2. Weeks 12–18: Structural steel detailing & foundation pack. Fabricator issues 3D Tekla/CAD general arrangement drawings and holding-down bolt setting-out plans for engineer sign-off.
  3. Weeks 16–22: Site strip, pads & 14-day BCMS notice. Lodge BCMS Commencement Notice 14–21 days ahead. Excavate pads, pour concrete with cast-in bolts and allow 7–14 days curing while steel fabricates.
  4. Weeks 22–25: Articulated delivery, crane erection & cladding. Primary portal frames bolt up in 2 to 5 days; purlins, roof PIR panels, rooflights, gutters, wall cladding and shutters close the building tight in 1 to 2 more weeks.
  5. Weeks 25–28: Internal C35 floor slab, M&E & BCAR CCC. Pour power-floated concrete slab under dry roof cover, wire 3-phase boards and lighting, pass Part L airtightness test and lodge the Certificate of Compliance on Completion.

Price my steel building

Four quick taps and our Irish guide price shows before we ask for a phone number. One local fabricator rings you, not five.

A commercial steel workshop, around 150 m² (80 to 200 m²), insulated shell with pads and C35 concrete slab: €84,000 to €118,500 (€560–€790/m²), ex VAT.

Step 1 of 5

What kind of steel building?

Pick the closest match. The fabricator confirms span and eaves height on site.

How the m² price is worked out

Figures reflect going Irish supply-and-erect rates ex VAT for CE-marked IS EN 1090-2 portal-frame buildings at typical 4 m to 6 m eaves. Shell rates cover fabricated columns, rafters, purlins, wind bracing, sheeting, gutters and erection on a prepared base. Insulated options add 60–100 mm PIR composite panels and roller doors. Slab options add excavated pad footings and a 150–200 mm power-floated C35 floor. Exposed Atlantic wind zones, rock excavation, three-phase ESB connections and BCAR fees are priced on survey.

What delays Irish steel builds most often

  • Late holding-down bolt sign-off. Fabricators will not cut steel until client and engineer sign the general arrangement drawing and anchor bolt grid.
  • Wet winter groundworks without crane stone. Trying to track a 40-tonne crane across soft mud stalls erection day and triggers wasted crane standing fees.
  • Custom RAL composite panel lead times. Standard Irish colours (anthracite RAL 7016, goosewing grey, juniper green, slate blue) roll fast; bespoke colours add 3–5 weeks.
  • Waiting until steel is up to apply for ESB Networks. Apply for 3-phase MIC months earlier so power is live for commissioning shutters and heat pumps.

Key questions before ordering structural steel

How fast can a 200 m² steel workshop be erected on site once concrete pads cure?

Once pads are cured and hardcore crane access is ready, an experienced crew typically erects the steel frame, roof and wall PIR cladding, flashings and doors in 1 to 2 weeks.

Can steel be fabricated while concrete foundations are being poured?

Yes. Overlapping the 6–10 week hot-rolled fabrication slot with pad foundation excavation and curing is the standard way to keep overall build programmes tight.

When can the concrete floor slab be poured?

Most contractors pour the power-floated concrete slab immediately after the roof and wall cladding go on, protecting fresh concrete from Irish rain and wind-burn.

When can I legally move stock or staff into a new commercial steel building?

Once your Assigned Certifier and Builder lodge the Certificate of Compliance on Completion (CCC) and the local Building Control Authority validates it on BCMS.

Every steel building page and engineering guide

Grey steel-clad commercial workshop and trade depot with three white roller shutter doors on a gravel yard

Check your per-m² budget before a fabricator rings

Pick the building type, rough m² footprint and cladding or slab scope. When you want a written tender, your details go to a single Irish steel fabricator in your county.