Pad foundations and power-floated concrete slabs
Complete industrial groundworks for an Irish steel building (pad foundations, compacted Clause 804 stone, damp-proof membrane and a 150–200 mm power-floated C35/45 concrete floor slab with A393 mesh or steel fibres) typically run €150 to €240/m² ex VAT on good bearing ground.
Sub-base compaction, reinforced concrete column pads, holding-down bolt cages and industrial C35/45 floor slabs.
Free, no obligation. One local fabricator prices it, not five.
- €150–€240/m²pads + C35 power-floated floor slab
- 150–200 mmcommercial C35/45 slab thickness
- A393 / fibressteel mesh or macro-fibre reinforcement
- 7–14 daysminimum pad cure before crane lift

How portal-frame loads reach the ground
A steel portal frame does not rest evenly along a perimeter strip trench like a block house. Vertical roof weight, lateral wind push and severe roof uplift all concentrate down through each steel column baseplate into individual reinforced concrete pad foundations. On a 15 m to 20 m span commercial unit, each perimeter pad commonly measures 1.2 m to 1.8 m square and 500 mm to 750 mm deep, reinforced with a bottom and top steel rebar cage and cast-in holding-down bolts positioned via plywood templates.
Light garage / cold-rolled base (150 mm)
€150–€185/m²
Compacted stone, 1200-gauge DPM, 150 mm C35 concrete with A252/A393 mesh and thickened perimeter ring beam.
Commercial workshop slab (175–200 mm)
€175–€215/m²
Excavated reinforced column pads, 200 mm C35/45 floor, A393 mesh or steel fibres, power-floated dust-sealed finish.
Heavy warehouse / racking slab (200–250 mm)
€210–€260/m²
Laser-screeded FM2 flatness, double mesh or heavy steel fibre dosing, armoured expansion joints at bays.
Price my steel building
Four quick taps and our Irish guide price shows before we ask for a phone number. One local fabricator rings you, not five.
A commercial steel workshop, around 150 m² (80 to 200 m²), insulated shell with pads and C35 concrete slab: €84,000 to €118,500 (€560–€790/m²), ex VAT.
How the m² price is worked out
Figures reflect going Irish supply-and-erect rates ex VAT for CE-marked IS EN 1090-2 portal-frame buildings at typical 4 m to 6 m eaves. Shell rates cover fabricated columns, rafters, purlins, wind bracing, sheeting, gutters and erection on a prepared base. Insulated options add 60–100 mm PIR composite panels and roller doors. Slab options add excavated pad footings and a 150–200 mm power-floated C35 floor. Exposed Atlantic wind zones, rock excavation, three-phase ESB connections and BCAR fees are priced on survey.
Six concrete and civils checks before pouring
- Trial hole soil check before quoting civils. Excavating two test pits confirms depth to stiff boulder clay or bedrock and avoids surprise rock-breaking or piling extras.
- Cast-in bolts vs resin chemical anchors. Hot-rolled portals normally cast J-bolts or anchor cages straight into wet concrete pads using the steel fabricator's exact setting-out drawing.
- Perimeter rebate / weather step. Stepping the outer cladding ledge 25–40 mm lower than the finished floor keeps wind-driven rain outside the roller doors and base flashings.
- Under-slab ducts and drainage gullies. Lay ESB power ducts, foul waste pipes for toilets, wash-bay oil interceptors and forklift ramp falls before the mesh goes down.
- Saw-cut contraction joints the day after pouring. Power-floated slabs cut on a 4.5 m to 6 m bay grid prevent random shrinkage cracking across the finished floor.
- Allow pads to cure before heavy cranes roll in. Concrete pads typically reach safe erection strength at 7 to 14 days (confirming cube test strength on BCAR jobs).
Related steel building guides
Hot-rolled I-beam framesCE-marked IS EN 1090-2 welded universal beams for wide spans and cranes.
Commercial workshops100 to 300 m² hot-rolled steel depots, roller shutters and power-floated floors.
Industrial warehouses300 to 1,000 m²+ high-eave logistics units, dock levellers and Part L specs.
Build timeline & erectionPlanning, BCAR, shop drawings, EN 1090 fabrication and crane erection weeks.
Commercial VAT & RCT13.5% vs 23% VAT, the two-thirds rule, VAT reverse charge and eRCT rates.
Steel building cost per m²Complete Irish €/m² breakdown from shell to insulated turnkey and civils.Key questions before ordering structural steel
How much does an industrial power-floated concrete slab cost per m² in Ireland?
Supplying stone sub-base, DPM, reinforcement, pad footings, C35/45 concrete and power-floating typically costs €150 to €240/m² ex VAT on straightforward level ground.
Should I pour the floor slab before or after erecting the steel frame?
On commercial portal buildings, column pads are poured first, the steel frame and roof cladding go up to create a dry sheltered cover, and the power-floated floor slab is poured cleanly indoors out of the rain.
Are steel fibres better than A393 rebar mesh in a workshop slab?
Both perform cleanly when engineered to the forklift axle and racking leg loads. Steel fibres speed up laser-screed pours on large warehouses; A393 mesh remains standard on 100–300 m² workshops and under heavy vehicle lifts.
Who designs the pad foundation sizes for a steel building?
The steel fabricator supplies the column base reactions (vertical load, horizontal thrust and uplift); your structural or civil engineer sizes the reinforced concrete pads to match your ground bearing pressure.
Every steel building page and engineering guide
Building types
Engineering & civils

Check your per-m² budget before a fabricator rings
Pick the building type, rough m² footprint and cladding or slab scope. When you want a written tender, your details go to a single Irish steel fabricator in your county.